Kings Modernization Phase II

Location: 451 Clarkson Avenue, Brooklyn NY 11203

Description:

The second phase of the campus-wide modernization project provides a new five-story 262,000 SF diagnostic and treatment building.  It is connected at all floor levels by a fully enclosed bridge link to the new bed tower, completed in 2001.  Construction of this building began in June 2002 and was occupied in 2006. The project budget for this phase was $145 million.  The new building houses state-of-the-art facilities for emergency care, imaging and other diagnostic and treatment modalities, surgical suite and labor & delivery suite.

New York Construction


Management:  DASNY
Architect:  Skidmore, Owings & Merrill, LLP (SOM)
Schedule:  
Completion - Occupancy 2006
Click on Image to enlarge

© 2006 The City of New York. All rights reserved